We're getting close to the home stretch for this project.... As of the last post, only 2 arms, sewing on buttons, weaving in ends, and repairing two dropped stitches is ALL that remains. Ha. :-)
At the beginning of this section, I have 3 full brown skeins available for the arms and 14g of Skein #7 that I will reserve for button sewing.
AND.... we've reached the warm part of the year. Progress on this project has slowed way down.
Since it will be 100F today, I think the responsible thing to do is to recognize that very little work will be completed on this project over the next few months. Which means it is essentially in Time Out and I will be focusing on much smaller projects such as socks for the near term.
As of this writing, I am about half-complete with the first arm.
Skein duration:
- #1 (11/2/24 - 12/10/24) 5wks 3days
- #2 (12/10/24 - 12/30/24) 2wks 6days
- #3 (12/30/24 - 1/6/25) 1 week
- #4 (1/6/25 - 1/18/25) 1wk 5days
- #5 (1/18/25 - 2/5/25) - 2wks 4days - 14 g remain
- Green (2/5/25 - 2/6/25) - 2days - 22 g remain (begin body stripes)
- Orange (2/6/25 - 2/8/25) - 3days - 23g remain
- #5 (2/8/25 - 2/9/25) - 2days - 11 g remain
- Orange (2/9/25) - 1day - 18 g remain
- Green (2/10/25 - 2/14/25) - 5days - 17 g remain (complete body stripes)
- #5 (2/14/25 - 2/20/25) - 6days (begin hem)
- #6 (2/20/25 - 2/25/25) - 5days - 20g remain (complete hem, bind off pending)
- TINK Body Hem (2/27/25 - 3/6/25) - 8days
- #5 (3/6/25 - 3/22/25) - 2 wks 2 days (begin re-Knitting Body Hem with smaller needles, US3)
- #6 (3/22/25 - 3/23/25) - 2 days (complete and bind-off Body Hem) - 19g remain
- Pickup Collar/Button Band Stitches (3/24/25 - 3/30/25) - 6days
- #6 (3/30/25 - 4/10/25) - 11days (begin Button Band/Collar, US3)
- #7 (4/10/25 - 4/22/25) - 12days (complete Button Band/Collar and Bind off) - 14g remain
- #8 (4/23/25 - 6/4/25) - 6wks (begin Arm #1, on hold for the summer) - 10g remain
Happy Fiber Arts Friday!